EasyBases Example Build

Customer Build by EasyBases Team

The following photographs were taken by one of our customers while our team set everything up and we thought it a perfect example to demonstrate some of the benefits of EasyBases.

  • The siting position had well compacted soil with bedded-in but uneven paving tiles, providing the exact situation EasyBases levelling feet were designed for.
  • This installation is an example of a site where the least possible preparation is required.
  • The 10’x12′ frame was supported with our Aluminum feet, including extras in the centre to improve load distribution.
  • The customer wanted a tiled surround to the shed that could be used to add ornaments or planters.
  • The combined height of the feet and EasyFrame was chosen to ensure any ground level flooding would have to reach about 10″ before making contact with the bottom of the shed. Due to considerations inherent to buildings on ‘stilts’, if intending to support a complete frame above this height, we would recommend contacting us for advice on custom options and new components that are in development.
  • By request during planning, spare tiling/masonry on-site was used to provide extra grounding for tiles and simplify levelling.
  • With the whole job completed in five hours, this is also an example of the quickest type of installation EasyBases can provide.
Area cleared on previous day
Frame built with feet ready for positioning after 90 minutes
EasyFloor tiles installed with all feet in place and levelled. 3 hours.
Shed installed in time for lunch! 5 hours start to finish.
Scroll to Top